Dependencies

Action Item Code Administrator Requirements / Dependencies Waiting Period
  ACNA Telcordia articles of incorporation / organization 10 business days
  OCN NECA articles of incorporation State Commission Approval 10 business days
  RAO Telcordia OCN, CMDS provider if hosted  
  CLLI Telcordia OCN, switch type, longitude / latitude 10 business days
  CIC LEC / NANPA OCN, ACNA, Switch CLLI, 911 orders, EF orders, submit to LEC with order for FGD trunks depends on LEC
  NRUF, PAS   OCN, FRN, desired rate centers  
  NXX NANPA / NEUSTAR state certification, interconnect agreement, OCN, AOCN, RAO, switch CLLI, NRUF, PAS forecast respond within 10 days
  Point Codes Telcordia location of switch, # of signaling points 10 business days
  TRS # NECA OCN, ACNA  
Joint Planning Meeting   LEC OCN, ACNA, CLEC profile, trunk forecast, Network Interconnection Sheets, 911 worksheets  
ASR / LSR system access   LEC Joint Planning Meeting  
NPAC agreement   NPAC OCN, ACNA, TRS #  
CMDS provider   RBOCs or Telcordia OCN, ACNA  
SS7 Links   SS7 provider Point Codes, OCN, ACNA, SS7 agreement, ASR system access if ordering through LEC  
911 Trunks   dedicated 911 provider Joint Planning Meeting, ASR system access if LEC is provider and requires CLEC to write orders (varies from company to company)  
Entrance Facilities     OCN, ACNA, Switch CLLI, Joint Planning Meeting, ASR system access  
LIS trunking     OCN, ACNA, Switch CLLI, Joint Planning Meeting, ASR system access, 911 trunk orders  
OS/DA trunks   LEC or OS provider OS/DA agreement, ASR system access if LEC is the provider  

Last Updated on 4/29/04
By Mary Lou Carey and Fred Goldstein